The contractor building the rental car lobby at Orlando International Airport’s Terminal C missed its June 2025 deadline and faces up to $7.4 million in potential penalties, with completion not expected until late June 2026. The Greater Orlando Aviation Authority has issued a formal liquidated damages notice to The Weitz Company; the contract specifies $20,000 […]